How to set up fine stone concrete pump before operation

2018-07-10 15:11:28

China’s construction industry is booming, and the number of high-rise buildings is increasing. Especially after the popularization and promotion of commercial concrete, fine stone concrete pumps are used more and more in engineering construction because they are durable and of high quality. What settings do we need to make before operation?

1. After the concrete pump reaches the set position, use the jack to adjust its height, so that the trailer concrete pump travel wheel is off the ground, and the leg is firmly fixed with the leg latch. Ensure that the hopper door switch is free and easy to clear; if the concrete pumping machine position is not changed for a long time, the tire can be removed.

2. When pumping from low pressure state to high pressure state, the portable concrete pump must be re-fixed to make it firm and reliable.

3. There must be 1 meter working space around the pump for operation and maintenance.

portable concrete pump

4. Small products should be kept away from slopes, dams, pits and trenches when setting up. It is necessary to consider whether it is convenient to mix the concrete mixer truck or the on-site mixing and feeding, and shorten the pipeline layout as much as possible.

5, small fine stone concrete pump must be placed on a firm and flat ground, it is best to cast a flat concrete foundation, while building a simple work shed.

6. Around the site where the concrete pump is installed, ensure that the water source is sufficient, the power supply is reliable, and the use is safe. Cables with sufficient wire diameter must be equipped according to the motor power to ensure the safety of the motor. And set up the lighting equipment that should be equipped.

The fine stone concrete pump is mainly used for the transportation of fine stone concrete or mortar. It can be used for floor heating construction, mortar pumping, etc. It is an ideal conveying equipment in construction. As long as it is a large-scale mechanical equipment, we must fully prepare before the construction. For the fine stone concrete pump, it is no exception. The grinding knife does not mistake the woodworker, and sufficient preparation can ensure the smooth construction.